  661. Using the table in the Special window, Which task is completed?
  A. dig hole
  B. remove debris
  C. survey
  D. set forms
  E. place concrete
  ANS: B
  
  662. Using the situation stated in the Special window, what is the cost performance index for Case #9?
  A. 1.10
  B. 1.91
  C. 0.83
  D. 1.20
  E. None of the above
  ANS: A
  
  663. Using the WBS shown in the Special window, a typical work package would be:
  A. Software development
  B. Systems design
  C. Coding
  D. A, B, and C
  E. None of the above.
  ANS: E
  
  664. Which of the statements regarding benefit-cost analysis in the Special window are true?
  A. 1 and 2
  B. 2 and 3
  C. 1 and 3
  D. 1, 2 and 3
  E. None of the above.
  ANS: C
  
  665. Using the cumulative cost curve in the special window, height B represents
  A. actual cost to date
  B. total budgeted costs for the project
  C. planned cost for month 6
  D. cost variance
  E. earned value
  ANS: B
  
  666. Using the situation stated in the Special window, a comparison of the cost variance of August as compared to July shows that the magnitude
  ($ value) of the variance has _____ and the percentage change has _____.
  A. Become worse, become worse
  B. Become worse, improved
  C. Improved, increased
  D. Improved, become worse
  E. None of the above are correct
  ANS: B
  
  667. Using the situation shown in the Special window and assuming continues efficiency for work-in-progress and fixed price contract for task four.
  The estimate at completion is:
  A. K
  B. K
  C. K
  D. K
  E. indeterminate
  ANS: C
  
  668. Using the scenario in the special window, the project manager appears to be a _____ manager.
  A. 1, 9
  B. 9, 1
  C. 1, 1
  D. 9, 9
  E. 5, 5
  ANS: E
  
  669. Using the scenario in the special window, the project manager:
  A. will probably spend the weekend reviewing the data.
  B. Won't ask for the report again.
  C. Has a preference for written communication.
  D. Has chosen an inappropriate medium.
  E. Is experiencing communication overload.
  ANS: E
  
  670. In which of the following scope management processes are subject matter experts used?
  A. Initiation
  B. Scope planning
  C. Scope Definition
  D. Scope change control
  E. Scope verification
  ANS: A
  
  

延伸阅读

文章来源于领测软件测试网 https://www.ltesting.net/


关于领测软件测试网 | 领测软件测试网合作伙伴 | 广告服务 | 投稿指南 | 联系我们 | 网站地图 | 友情链接
版权所有(C) 2003-2010 TestAge(领测软件测试网)|领测国际科技(北京)有限公司|软件测试工程师培训网 All Rights Reserved
北京市海淀区中关村南大街9号北京理工科技大厦1402室 京ICP备10010545号-5
技术支持和业务联系:info@testage.com.cn 电话:010-51297073

软件测试 | 领测国际ISTQBISTQB官网TMMiTMMi认证国际软件测试工程师认证领测软件测试网