  631. Using the situation stated in the Special window, which WBS element is behind schedule but under budget?
  A. Element P
  B. Element Q
  C. Element R
  D. Element S
  E. None of the above.
  ANS: D
  
  632. Using the situation stated in the Special window, which WBS element has a favorable cost variance of 0?
  A. Element P
  B. Element Q
  C. Element R
  D. Element S
  E. None of the above.
  ANS: C
  
  633. Using the situation stated in the Special window, the cost performance index (CPI) for WBS Element R is:
  A. 0.875
  B. 1.14
  C. 0.952
  D. 0.833
  E. 1.20
  ANS: B
  
  634. Using the situation stated in the Special window, the schedule performance index (SPI) for WBS Element P is:
  A. 1.10
  B. 0.90
  C. 0.956
  D. 1.15
  E. 0.869
  ANS: A
  
  635. Using the situation stated in the Special window, WBS Element Q is _____ budget by _____ percent.
  A. Over, 16.66
  B. Under, 16.66
  C. Over, 10.0
  D. Under, 10.0
  E. None of the above.
  ANS: A
  
  636. Using the situation stated in the Special window, a comparison of the cost schedule of August as compared to July shows that the magnitude
  ($ value) of the variance has _____ and the percentage change has _____.
  A. Become worse, become worse
  B. Become worse, improved
  C. Improved, increased
  D. Improved, become worse
  E. None of the above are correct
  ANS: E
  
  637. Using the situation stated in the Special window, the total price variance of direct material is:
  A. ,245
  B. -36
  C. -79
  D. %content%.69
  E. ,994
  ANS: C
  
  638. Using the situation stated in the Special window, the labor rate cost variance is:
  A. ,927
  B. ,329
  C. 6
  D. -%content%.22
  E. .36
  ANS: D
  
  639. Using the situation stated in the Special window, what is the total fixed costs for manufacturing the widgets?
  A. ,000
  B. ,000
  C. ,270
  D. ,335
  E. ,000
  ANS: E
  
  640. Using the figure in the Special window, The critical path is:
  A. A-B-G
  B. C-G
  C. C-D
  D. E-F
  E. A-B-G and C-D
  ANS: B
  
  

延伸阅读

文章来源于领测软件测试网 https://www.ltesting.net/


关于领测软件测试网 | 领测软件测试网合作伙伴 | 广告服务 | 投稿指南 | 联系我们 | 网站地图 | 友情链接
版权所有(C) 2003-2010 TestAge(领测软件测试网)|领测国际科技(北京)有限公司|软件测试工程师培训网 All Rights Reserved
北京市海淀区中关村南大街9号北京理工科技大厦1402室 京ICP备2023014753号-2
技术支持和业务联系:info@testage.com.cn 电话:010-51297073

软件测试 | 领测国际ISTQBISTQB官网TMMiTMMi认证国际软件测试工程师认证领测软件测试网