  601. Most project management leadership theories focus on all of the following except:
  A. Personal characteristics of the project manager
  B. The situation at hand
  C. Personal traits of the subordinates
  D. Behavioral styles of the project manager
  E. Usefulness of authority and power in leadership
  ANS: C
  
  602. Project trade-offs vary between
  A. risk, cost and schedule.
  B. direct cost, indirect cost, and resource availability
  C. quality, schedule and time
  D. cost, quality and schedule
  E. contract terms, scope and budget
  ANS: D
  
  603. The following individuals are responsible for determining the content of the Communications Management Plan.
  A. Project Sponsor
  B. Task Manager(s)
  C. Director of Communications
  D. Project Manager
  E.
  ANS: D
  
  604. When comparing the cost of competing projects, which of the following is typically NOT considered?
  A. Opportunity costs.
  B. Direct costs.
  C. Sunk costs.
  D. Indirect costs.
  E. Burden rates.
  ANS: C
  
  605. Input into the Communications Management Plan includes the following information from the stakeholder analysis:
  A. Information needs
  B. Information content
  C. Frequency of distribution
  D. Method of distribution
  E. All of the above
  ANS: E
  
  606. The computation for Cost Performance Index is:
  A. BCWP/ACWP
  B. BCWP-ACWP
  C. BCWP-BCWS
  D. ACWP/BCWP
  E. ACWP-BCWS
  ANS: A
  
  607. We assign human and non-human resources in the _____ phase of the budget.
  A. conceptual
  B. planning
  C. development
  D. implementation
  E. close-out
  ANS: D
  
  608. Which of the following can the project manager use as a means of measuring project team effectiveness?
  A. Absenteeism
  B. Sponsor-approved salary increases
  C. Efficiency of the team
  D. Turnover of personnel
  E. Grievances
  ANS: C
  
  609. Project alternatives are examined during the _____ phase of the project
  A. conceptual
  B. finish
  C. development
  D. implementation
  E. A and C
  ANS: E
  
  610. Project leadership requires that the project manager pay attention simultaneously to the:
  A. Tasks to be performed and needs of the team
  B. Quantity and quality of the work to be performed
  C. Efficiency and effectiveness of the team
  D. Time, cost and performance deliverables
  E. All of the above
  ANS: E
  
  

延伸阅读

文章来源于领测软件测试网 https://www.ltesting.net/


关于领测软件测试网 | 领测软件测试网合作伙伴 | 广告服务 | 投稿指南 | 联系我们 | 网站地图 | 友情链接
版权所有(C) 2003-2010 TestAge(领测软件测试网)|领测国际科技(北京)有限公司|软件测试工程师培训网 All Rights Reserved
北京市海淀区中关村南大街9号北京理工科技大厦1402室 京ICP备10010545号-5
技术支持和业务联系:info@testage.com.cn 电话:010-51297073

软件测试 | 领测国际ISTQBISTQB官网TMMiTMMi认证国际软件测试工程师认证领测软件测试网