PMP认证考试试题精选(55)

发布: 2007-5-26 23:09 | 作者: 佚名 | 来源: 互连网 | 查看: 33次 | 进入软件测试论坛讨论

领测软件测试网
  541. Which influence reflects an informal organization?
  A. formal authority
  B. reward power
  C. referent power
  D. expert power
  E. penalty
  ANS: C
  542. A life cycle project manager tends to have the following characteristics:
  A. balanced training
  B. stronger administrative skills than technical skills
  C. stronger technical skills than administrative skills
  D. stronger human resource skills
  E. None of the above.
  ANS: B
  543. In acceptance sampling, if the sample size is kept the same but the acceptance number is increased, which of the following will be true:
  A. buyer's risk will decrease
  B. vendor's risk will decrease
  C. producer's risk will decrease
  D. consumer's risk will increase
  E. C and D only
  ANS: E
  544. Risks include the following types:
  A. Business risk
  B. pure risk
  C. Insurable risk
  D. A and B
  E. All of the above.
  ANS: E
  545. Traits of a participative manager include:
  A. being accessible
  B. being an effective delegator
  C. holding social gatherings
  D. All of the above.
  E. A and C
  ANS: D
  546. All of the following statements about acceptance sampling are true except:
  A. Acceptance sampling plans are beneficial when the cost of inspection is high and the resulting loss of passing nonconforming units is not great.
  B. Acceptance sampling plans are necessary when destructive inspections are required.
  C. Acceptance sampling plans are never effective at rejecting nonconforming units as 100 percent inspection, even when the inspection process is
  very tedious.
  D. Acceptance sampling plans do not directly control the quality of a series of lots; they instead specify the risk of accepting lots of given quality.
  E. Acceptance sampling plans are not very effective for inspecting small lots of custom-made products.
  ANS: C
  547. Interfacing with the customer after project go-ahead is the responsibility of:
  A. Project sponsor
  B. Project team
  C. Project manager
  D. Functional manager
  E. All of the above are possible, based upon the size and complexity of the project
  ANS: C
  548. Parametric cost estimating involves
  A. using the WBS to do bottom up estimates
  B. defining the perimeters of the life-cycle
  C. calculating the individual estimates of work packages
  D. using a statistical model to estimate costs
  E. A and C
  ANS: D
  549. Risk exposure refers to _____ .
  A. the amount at stake.
  B. what might happen.
  C. the likelihood of something
  D. who is going to be held accountable
  E. All of the above.
  ANS: A
  550. The compromise conflict resolution technique
  A. is necessary when both participants must win.
  B. results in both sides losing
  C. is used when resolution is more important than relationships
  D. B and C
  E. All of the above.
  ANS: B
  
  
  
  
  

延伸阅读

文章来源于领测软件测试网 https://www.ltesting.net/


关于领测软件测试网 | 领测软件测试网合作伙伴 | 广告服务 | 投稿指南 | 联系我们 | 网站地图 | 友情链接
版权所有(C) 2003-2010 TestAge(领测软件测试网)|领测国际科技(北京)有限公司|软件测试工程师培训网 All Rights Reserved
北京市海淀区中关村南大街9号北京理工科技大厦1402室 京ICP备2023014753号-2
技术支持和业务联系:info@testage.com.cn 电话:010-51297073

软件测试 | 领测国际ISTQBISTQB官网TMMiTMMi认证国际软件测试工程师认证领测软件测试网