PMP认证考试试题精选(35)

发布: 2007-5-26 23:09 | 作者: 佚名 | 来源: 互连网 | 查看: 30次 | 进入软件测试论坛讨论

领测软件测试网
  351. In a matrix organizational form, which factor(s) make it difficult for a project manager to provide a valid input into the employee's performance
  review?
  A. Not working directly with the assigned functional employees
  B. Employees spend only a short amount of time assigned to the project
  C. Not being knowledgeable enough to evaluate employees on technical judgment
  D. All of the above
  E. A and B only
  ANS: D
  
  352. Upon completion of 75% of the project, the original schedules and cost estimates that were submitted at the inception of the project are
  referred to as the:
  A. Baseline costs
  B. Budgeted costs.
  C. Estimates upon completion costs
  D. Scheduled costs
  E. None of the above
  ANS: A
  
  353. Which of the following is not a definition to determine a product's ability to operate as intended?
  A. distance
  B. performance
  C. function
  D. condition
  E. All are definitions
  ANS: E
  
  354. A work breakdown structure is most useful for:
  A. identifying individual tasks for a project
  B. scheduling the start of tasks
  C. developing a cost estimate
  D. determining potential delays
  E. A and C
  ANS: E
  
  355. Reaching an understanding of concessions is accomplished in the _____ stage of negotiations.
  A. protocol
  B. probing
  C. scratch bargaining
  D. closure
  E. agreement
  ANS: D
  
  356. The primary consideration of product management is to know the _____.
  A. probability of product's performance with specified parameters
  B. ability the product has to perform its intended function
  C. ability of a product to be produced within existing parameters
  D. functionality the product will provide over its useful life
  E. All of the above
  ANS: D
  
  357. The reason that cost management is so difficult in project management is that:
  A. Projects by definition and nature are non-recurring events and are therefore difficult to predict.
  B. There are no tools for identifying project tasks.
  C. Project managers do not care about tracking costs, as only schedules are important to all project managers.
  D. A and B only
  E. B and C only
  ANS: A
  
  358. Using visual aids during management/customer presentations will:
  A. hold the interest of the audience
  B. strengthen the learning process by adding a visual dimension to the auditory dimension
  C. stay in view longer, thus bringing back listeners who may have strayed
  D. All of the above.
  E. A and B only
  ANS: D
  
  359. Which of the following organizational forms would be likely to have an individual with the title of Vice President for Project Management?
  A. Classical / traditional
  B. Pure project
  C. Matrix
  D. Project coordinator
  E. None of the above
  ANS: C
  
  360. A contract is legally binding and must comprise all but one of the following:
  A. legal capacity
  B. mutual assent
  C. approved negotiations
  D. consideration
  E. legality
  ANS: C
  
  

延伸阅读

文章来源于领测软件测试网 https://www.ltesting.net/


关于领测软件测试网 | 领测软件测试网合作伙伴 | 广告服务 | 投稿指南 | 联系我们 | 网站地图 | 友情链接
版权所有(C) 2003-2010 TestAge(领测软件测试网)|领测国际科技(北京)有限公司|软件测试工程师培训网 All Rights Reserved
北京市海淀区中关村南大街9号北京理工科技大厦1402室 京ICP备10010545号-5
技术支持和业务联系:info@testage.com.cn 电话:010-51297073

软件测试 | 领测国际ISTQBISTQB官网TMMiTMMi认证国际软件测试工程师认证领测软件测试网