PMP认证考试试题精选(39)

发布: 2007-5-26 23:09 | 作者: 佚名 | 来源: 互连网 | 查看: 35次 | 进入软件测试论坛讨论

领测软件测试网
  391. The purpose of a dummy activity in an activity-on-arrow diagram is to:
  A. Identify a task that could be replaced by another.
  B. Take the slack time into account.
  C. Show a task that is not necessarily needed.
  D. Denote a milestone.
  E. Show a dependency relationship.
  ANS: E
  
  392. When planning, organizing, coordinating, and controlling a project an important human resources skill or ability would be
  A. Building multi-disciplinary teams
  B. Managing conflict
  C. Communicating orally and in writing with all levels of personnel
  D. Involving senior management
  E. All are important
  ANS: E
  
  393. Which is not a negotiation tactic?
  A. Imposing deadlines
  B. surprises
  C. person with authority is absent
  D. reasoning together
  E. all are negotiations tactics
  ANS: E
  
  394. Which of the following is referred to as sunk cost:
  A. management reserve
  B. contingency fund
  C. cost budgeted for construction under water
  D. expended funds over which there is no further control
  E. forecasted budget over-runs
  ANS: D
  
  395. A project manager believes that modifying the scope of the project may provide added value for the customer. The project manager should:
  A. Change the scope baseline
  B. Prepare a variance report
  C. Call a meeting of the configuration control board
  D. Change the project's objectives
  E. Postpone the modification until a separate enhancement project is funded after this project is completed according to the original baseline
  ANS: E
  
  396. As a project is carried out and slack time is consumed on individual tasks, the slack left over for the remaining tasks is:
  A. Insignificant.
  B. Reduced.
  C. Unchanged.
  D. Increased.
  E. Doubled.
  ANS: C
  
  397. Group brainstorming encourages all of the following except:
  A. Team building
  B. Uninhibited verbalization
  C. Decision making
  D. Analysis of alternatives
  E. Convergent thinking
  ANS: E
  
  398. Non-conformance penalties are a form of _____.
  A. quality incentive
  B. risk sharing
  C. contract negotiations
  D. quality assurance programs
  E. None of the above.
  ANS: C
  
  399. Risk Event Status is defined as _____ .
  A. Risk Probability x Amount At Stake.
  B. the severity of the consequences.
  C. how likely the event is to occur with risk.
  D. (Cost + Benefit + Business Risk) / Insurable Risk.
  E. B and C
  ANS: A
  
  400. There are hard causes of conflict (e.g. conflicting schedules) and soft causes. Soft causes are as important as hard causes. Soft causes
  include diversity of disciplinary expertise, _____, and the project manager's power of reward and punishment.
  A. Performance tradeoffs
  B. Ambiguity of roles
  C. Administrative procedures
  D. Determining earned value
  E.
  ANS: B
  
  

延伸阅读

文章来源于领测软件测试网 https://www.ltesting.net/


关于领测软件测试网 | 领测软件测试网合作伙伴 | 广告服务 | 投稿指南 | 联系我们 | 网站地图 | 友情链接
版权所有(C) 2003-2010 TestAge(领测软件测试网)|领测国际科技(北京)有限公司|软件测试工程师培训网 All Rights Reserved
北京市海淀区中关村南大街9号北京理工科技大厦1402室 京ICP备2023014753号-2
技术支持和业务联系:info@testage.com.cn 电话:010-51297073

软件测试 | 领测国际ISTQBISTQB官网TMMiTMMi认证国际软件测试工程师认证领测软件测试网